The Resident District Commissioner Rwampara district Emmy Kateera Turyabagyenyi has ordered the removal of all roofing timbers used on Kagirirwe primary school, Bushwere health center 11 due to poor quality and kanyaga primary school.
This order comes after the Resident District Commissioner Rwampara district Emmy Kateera Turyabagyenyi was monitoring the three projects which are under construction in Bugamba and Mwizi sub counties.
The three projects under construction are 3classroom block at Kagirirwe primary school at a tune of 76 ugx million, staff quarters for health workers at Bushwere health center two which will cost ugx 59 millions.
The other is two classrooms at kanyaga primary school which will cost ugx 71 millions.
Kateera noted that what they had agreed with the constructors was not matching with a bill of quantities.
He says that they are going to call all constructors in the meeting at the district headquarters on Friday for questioning over what he called shoddy work.